VDOT says major I-95 delays next weekend

by | Sep 14, 2019 | Traffic

Northbound travelers on Interstate 95 will encounter major travel delays in the Fredericksburg area beginning in late afternoon on Saturday, September 21 through the morning of Sunday, September 22.

Lane closures are needed for 18 consecutive hours of paving, lane striping and preparation to finish building the transition point for drivers to enter three temporary travel lanes for I-95 northbound in the median.

I-95 motorists are strongly encouraged to choose an alternate route to avoid delays, especially through travelers with destinations outside the Fredericksburg area.

What’s Being Done

 Construction crews need to replace the existing I-95 northbound overpass of Route 17 at Exit 133 in Stafford County over the next 12 months. Two existing Route 17 overpass bridges – northbound and southbound – are being replaced as part of the I-95 Southbound Rappahannock River Crossing project.

To build the new overpass, all I-95 northbound traffic will be diverted to travel in temporary lanes in the median, parallel to the interstate.

The weekend work zone during Sept. 21-22 is the final step before the temporary lanes open. When lanes reopen at 10 a.m. Sunday, northbound I-95 traffic will begin traveling in the temporary lanes.

Over 18 hours, crews will put down around 2,000 tons of asphalt and 20,000 feet of lane markings, and place around 5,000 feet of concrete barriers.

What Drivers Can Expect

Beginning at 4 p.m. on Saturday, Sept. 21, I-95 northbound will be reduced to two lanes near the Rappahannock River bridge, which is located between the City of Fredericksburg and Stafford County.

I-95 northbound will be reduced to a single lane at 5 p.m. Saturday. The northbound exit ramp and entrance ramp at Exit 133, also known as a collector-distributor lane, will remain open. It will serve as a second northbound travel lane.

From 8:30 p.m. Saturday to 10 a.m. Sunday, Sept. 22, all I-95 northbound traffic will be diverted onto the collector-distributor lane.

Between 8:30 p.m. Saturday and 10 a.m. Sunday, northbound I-95 traffic can exit to Route 17, but Route 17 traffic cannot use the entrance ramps to access I-95 northbound. Detour signs for local traffic on Route 17 will be directed to use Route 1 northbound and Exit 136 (Centreport Parkway) to access I-95 northbound.

I-95 southbound will remain open in the Fredericksburg area during the Sept. 21-22 weekend work zone. Additionally, all I-95 southbound ramps at Exit 133 at Route 17 will remain open.

This work zone has been scheduled weather permitting. If the work zone is cancelled, it will be rescheduled for 4 p.m. Saturday, Sept. 28 through 10 a.m. Sunday, Sept. 29.

Weekend Work Zone

Performing this work in a single 18-hour period, during mostly overnight hours, will avoid disrupting travelers over multiple weeks of evening work.

These hours were identified using traffic analysis as the least disruptive time for work to be scheduled. Accomplishing the work over the weekend avoids delays to weekday commuter and commercial traffic.

To encourage travelers to use an alternate route, VDOT will:

 

  • Lift lane closures on Route 1 northbound in the Fredericksburg area during the work zone, and along Route 207 northbound in Caroline County and Route 301 northbound in Caroline and King George counties

 

  • Adjust signal timing on these alternate routes to meet additional demand

 

  • Use overhead message boards along the I-64, I-95, and I-295 corridors in Virginia to make motorists aware of lane closures ahead at Fredericksburg, and encourage travelers to use Exit 104 (Carmel Church) on I-95 to travel along Route 207 and Route 301

Stay Updated

Real-time updates on this work zone, lane closures and congestion will be available on 511Virginia.

Subscribe To Daily News Updates

Join our mailing list to receive the latest news from The Free Press

You have Successfully Subscribed!

Share This